of the implementation rate of the concrete structure of the capital’s parliament building
The implementation rate of the concrete structure of the main building exceeded 85%, noting that the concrete works reached 120,000 cubic meters of concrete out of a total of 160,000 cubic meters.
320 thousand cubic meters, the total amount of drilling in the capital’s administrative project
With the total amount of excavation inside the parliament building reached 320 thousand cubic meters, it is the largest proportion of drilling for a government building, and he explained that the parliament building takes place on an area of 26 acres, equivalent to 109 thousand square meters, and includes the main building of parliament, which consists of a basement, ground, and eight repeated floors with a height of 65 meters It contains a main hall with a capacity of 1000 members and offices for up to 3,200 employees.